Current Projects

Project code

Project name

The value of contract (Lt)

Implementation period/ Delay

В1

Interim Spent Fuel Storage Facility (ISFSF)

667 548 303, 80

Start: 2005-01-12
Delay:  44 months.  

В2/3/4

Solid Waste Management and Storage Facilities (SWMSF)

428 262 161,23

Start: 2005-11-30
Delay:  B2 - 54 months,  B3/4 - 47 months.

B9/1

INPP Unit 1 Turbine Hall Equipment Decontamination and Dismantling Project Development

25 790 020

Start: 2007-11-22
Equipment dismantling works have been started

B9/2

INPP Building V1 Equipment Dismantling and Decontamination Design Development

11 639 389

Start: 2009-01-14
The project is delayed

B9/5

INPP Boiler House Equipment Dismantling and Decontamination Design Development (119 building)

6 797 000

Start: 2009-05-05
Equipment dismantling works have been started

B12

Equipment and Consumables for In-line Decontamination at Unit 1

5 140 500

Start: 2010-01-12

B19

Landfill Facility for Short-lived Very Low Level Waste

21 354 637,5

Start: 2007-12-29
Delay: 24 months.

B25/1

Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste (Design)

35 911 050

Start: 2009-10-23
Delay: 4 months.

UP01
(B9/4)

INPP Unit 1 and 2 Reactor Dismantling and Decontamination Feasibility Study

-

Start: 2010-08-23