Current Projects
|
Project code |
Project name |
The value of contract (Lt) |
Implementation period/ Delay |
|
667 548 303, 80 |
Start: 2005-01-12 |
||
|
428 262 161,23 |
Start: 2005-11-30 |
||
|
INPP Unit 1 Turbine Hall Equipment Decontamination and Dismantling Project Development |
25 790 020 |
Start: 2007-11-22 |
|
|
INPP Building V1 Equipment Dismantling and Decontamination Design Development |
11 639 389 |
Start: 2009-01-14 |
|
|
INPP Boiler House Equipment Dismantling and Decontamination Design Development (119 building) |
6 797 000 |
Start: 2009-05-05 |
|
|
Equipment and Consumables for In-line Decontamination at Unit 1 |
5 140 500 |
Start: 2010-01-12 |
|
|
21 354 637,5 |
Start: 2007-12-29 |
||
|
Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste (Design) |
35 911 050 |
Start: 2009-10-23 |
|
|
INPP Unit 1 and 2 Reactor Dismantling and Decontamination Feasibility Study |
- |
Start: 2010-08-23 |