Archive for: 2011 January
2011-01-12 Ignalina NPP Has Additionally Earned 2.584 Million Litas for the Decommissioning Activity
During four months in 2010 the state enterprise Ignalina Nuclear Power Plant has sold the property unnecessary for the enterprise formed during implementation of the decommissioning projects for more than 2.584 million Lt (it was planned to sell the property for 2 million Litas). The money received will be used for the decommissioning activity financing. Read more
2011-01-07 The Completion Date of B1 Project Construction Works Has Been Pushed Back Because of the Contactors Default
The works on the constructional part of B1 project (Interim Spent Fuel Storage Facility – ISFSF), that should have been completed by the end of 2010, because of the contractors‘ failure to perform its obligations, are planned to be completed in March 2011. Read more