Decommissioning projects

Current Projects

* except infrastructure projects.
* the prices in GBP should be converted in litas according to currency exchange rate of that day.

 project code  project name  the price of the contract implementation period
B1 Interim Spent Fuel Storage Facility (ISFSF)

200 081 931.97 EUR

  • Contract signing - 12/01/2015
  • Construction commencement - 02/09/2009
  • Commercial operation - 04/05/2017
  • Fuel transportation completion 2022 III q.
В2/3/4

Solid Waste Management and Storage Facilities (SWMSF)

 196 799 807,89 EUR
  •  Start - 30/11/2005
2206

INPP Unit 1 Turbine Hall Equipment Decontamination and Dismantling (D&D) Project license documents development, Project B9/1

3 611 806 EUR
  • Start - 22/11/2007
  • Completion date - 28/11/2013

Performing dismantling works of equipment by project B9/1

implemented by INPP personnel 
  • Start - 2011-10-21
  • Forecast completion - 27/06/2019 /completed/
2213

INPP Unit 2 Turbine Hall Equipment Decontamination and Dismantling (D&D) Project license documents development, Project B9/1(2)

implemented by INPP personnel 
  • Start - 14/09/2011
  • Completion date - 31/10/2013
  • Updated license for D&D received- 18/06/2014

Performing dismantling works of equipment by project B9/1(2)

implemented by INPP personnel 
  • Start - 01/07/2014
  • Forecast completion - 22/04/2021
B9/2

INPP Building V1 Equipment Dismantling and Decontamination Design Development

1 710 986.58 EUR
  • Start - 14/01/2009
  • Completion of the first phase - 27/12/2013
  • The second phase will start after 2023
2214

INPP Unit D2 equipment dismantling and decontamination

   
2203

INPP Building A1 Equipment Dismantling and Decontamination Design Development

implemented by INPP personnel 
  • Start - 01/05/20132013
Performing dismantling works  
  • Completion - 2034
2207

Unit D1, D0 Equipment Dismantling and Decontamination Design Development

implemented by INPP personnel 
  • Start - 03/06/2013
  • Completion - 15/09/2015
Performing dismantling works    
 B19

Landfill Facility for Short-lived Very Low Level Waste

 6 189 750.00 EUR  
  • Start - 12/05/2008
B20 Modernisation of Bitumised Waste Storage Facility

 5540 000.00
 EUR

 
  •  Contract for the 1st stage 04/10/2018
B25/1

Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste (Design)

9 687 014 EUR
  • Start - 23/10/2009
B25/2 Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste (Construction and Commissioning)     
The contract is not signed
UP01  

Project 2101. Dismantling of Units 1 Reactor Facility

Project 2102. Dismantling of Units 2 Reactor Facility*

2102 – implementation will begin after the unloading of spent nuclear fuel from the reactor, the radiological characterization of Unit 2

 
  • Start - 2010-07
  • Forecast completion date - 2034-08
  Giluminio atliekyno projektas  
  • Start - 2019
  • Forecast completion - 2078
6101 Maišiagalos radioaktyviųjų atliekų saugyklos eksploatavimo nutraukimas 4 000 000 EUR
  • Start - 15/12/2016
  • Completion - 01/09/2023